Imerys: Tube Mill Optimization Project, Ryan Waltman, Dalton Beasley, Dyson Beasley, Tristan Mcmichael Dec 2023

Imerys: Tube Mill Optimization Project, Ryan Waltman, Dalton Beasley, Dyson Beasley, Tristan Mcmichael

Senior Design Project For Engineers

The Tube Mill Optimization Project is in partnership with Imerys for Tube Mill 81 at their Marble Hill site in Georgia. Tube Mill 81 is a dry ball mill that operates 24/7 and makes an intermediary product for Plant 3. Tube Mill 81 needs quality improvement and a production rate increase to meet demand. Imerys’s quality specification is between a particle size of 12-18 microns and an acceptable production rate of 5 tons per hour. This project focuses on the development and implementation of three solutions: increase the amps on the separator to increase production, replace missing classifier blades in …


Space Optimization And Process Improvement, Harith Alshareef Dec 2019

Space Optimization And Process Improvement, Harith Alshareef

Senior Design Project For Engineers

Siemens Energy warehouse located in Suwanee, GA runs out of space in the Precision Lab due to rapid growth, seasonal peaks, and poor space utilization. The objective of the project is to redesign the Precision Lab layout and improve the tool assessment process to increase efficiency, productivity, and profitability.

The first solution is to add shelves in the Precision lab as well as the Torque lab and reduce the honeycombing effect on the shelves, which results in a 120%-150% increase in the storage space. We propose adding Tablets that include barcode scanner features to reduce the time spent on the …