Open Access. Powered by Scholars. Published by Universities.®

Engineering Commons

Open Access. Powered by Scholars. Published by Universities.®

1984

International Conference on Case Histories in Geotechnical Engineering

Articles 31 - 60 of 239

Full-Text Articles in Engineering

Welcoming Remarks, Shamsher Prakash, John T. Park, Joseph H. Senne May 1984

Welcoming Remarks, Shamsher Prakash, John T. Park, Joseph H. Senne

International Conference on Case Histories in Geotechnical Engineering

No abstract provided.


Welcome Messages, Multiple Authors May 1984

Welcome Messages, Multiple Authors

International Conference on Case Histories in Geotechnical Engineering

No abstract provided.


A New Version Of Rectification For The Leaning Structures And Foundations, Yi-Ji Wang, Jian-Xin Yuan May 1984

A New Version Of Rectification For The Leaning Structures And Foundations, Yi-Ji Wang, Jian-Xin Yuan

International Conference on Case Histories in Geotechnical Engineering

A new version of the rectification technique tor the leaning structure and foundation developed by Wuhan Foundation Engineering Center was used to restore the tilted columns to their original position. The main idea of this new method is to apply adjusting loads on the foundation through anchors or short piles. According to the tilting conditions the anchors or piles can be installed at one side or at both sides of the tilting foundations. The loads can be applied in successive increments until the final desired positions were reached. By using this technique a tilted warehouse was completely restored to its …


Adjustable Columns Control Settlement Of Structure, F. B. Newman, A. M. Digioia Jr. May 1984

Adjustable Columns Control Settlement Of Structure, F. B. Newman, A. M. Digioia Jr.

International Conference on Case Histories in Geotechnical Engineering

A five-story precast concrete building was to be built on 10 to 130 feet of mixed cohesive and bouldery engineered fill. The initial estimates of total and differential settlement of shallow foundations for the structure were considered intolerable. After evaluating several options, it was concluded that providing a means of adjusting the building columns to "relevel" the structure as the foundations settled was the most cost-effective approach to the problem. The observed settlements were different than originally estimated, and some unanticipated settlement and adjustment problems did occur. However, the approach was successful and cost effective.


Bearing Capacity Of Piles Under Long-Term Vibration, Xu You Zai, Liu Yao Fu, Shi Yul Iang, Xin Su Lan May 1984

Bearing Capacity Of Piles Under Long-Term Vibration, Xu You Zai, Liu Yao Fu, Shi Yul Iang, Xin Su Lan

International Conference on Case Histories in Geotechnical Engineering

The Bearing capacity of piles under long-term vibration is herein discussed. A real case of continuous subsidence of vibrating pile foundations is presented with a set of vibratory loading tests in-situ and the characteristics of settlement-time curves are described. Analyses of the observed data are made and the additional plastic deformation induced in the soil strata under the piles is interpreted. Based on the test data, authors recommend a conception of long-term bearing capacity of piles to be used in the design of pile foundation under vibration instead of the conventional one, and a method of determination of bearing capacity …


Behaviour Of Bridge Abutment On Fractured Chalk, A. Marsland, A. P. Butcher May 1984

Behaviour Of Bridge Abutment On Fractured Chalk, A. Marsland, A. P. Butcher

International Conference on Case Histories in Geotechnical Engineering

Loading tests on 865 mm diameter plates showed that the fractured chalk was much more compressible than at other sites on the same deposit but it was still considered that slab foundations would be adequate for the bridges at most locations. Detailed measurements have been made on one of the bridge abutment foundations both during and following construction. Measurements were made of vertical pressures applied to the ground, lateral earth pressures acting on the abutment wall, settlements of the foundation slab, tilt of the wall, and vertical displacements in the ground below the foundations. These observations confirmed the adequacy of …


Caisson Design By Instrumented Load Test, D. J. Lane May 1984

Caisson Design By Instrumented Load Test, D. J. Lane

International Conference on Case Histories in Geotechnical Engineering

Three instrumented axial load tests were performed on 42 inch diameter caissons (drilled piers). These caissons were installed in marine sediments of dense sand overlain by soft sand-clay mixtures. Correlations were made with the Standard Penetration Test to develop design relationships. Production caissons were then designed based on these relationships. Test caissons were approximately 54 feet long and installed by the slurry displacement method. Test loads were carried to 1,000 tons. Mustran cells were used to determine loads in the caissons at different depths. Resulting data is presented graphically as load versus settlement, load versus depth (load distribution), and side …


Chimney Foundation On Drilled Piers, K. Y. C. Chung, L. D. Cundy May 1984

Chimney Foundation On Drilled Piers, K. Y. C. Chung, L. D. Cundy

International Conference on Case Histories in Geotechnical Engineering

This paper describes the design and compares predicted performance to actual responses of a drilled pier foundation supporting a 305m high chimney. The purpose was to evaluate laboratory and empirical side friction and end bearing criteria used in the pier design. Based on results of a subsurface exploration program, and consideration of vibration effects on nearby structures, a foundation system was designed consisting of 38 drilled piers capped with a concrete mat. The piers had an average diameter of 1.37m in soil and 1.22m in rock. The average length of pier was 15.63m including a rock socket 2.44m deep. Each …


Combined Earth And Rock Bearing Foundation - Hospital Humana Mexico City D.F., Michael R. Stomer, Pablo Girault, L. E. Wilson May 1984

Combined Earth And Rock Bearing Foundation - Hospital Humana Mexico City D.F., Michael R. Stomer, Pablo Girault, L. E. Wilson

International Conference on Case Histories in Geotechnical Engineering

This text describes the design and performance of a shallow spread footing foundation system for a large medical care facility in Mexico City. The project is unusual because the spread footings bear on a combination of basaltic lava and coarse sand fill containing angular lava fragments, the latter of which was densified using the dynamic deep compaction process. In the following narrative, the exploratory program is described, the geotechnical design and construction process is explained, and the inspection procedure for footings bearing on rock and soil is discussed. Further, the results of precise settlement monitoring for the structure are presented.


Damaging Settlements Of A Building Due To Gypsum Dissolution, Minh Phong Luong May 1984

Damaging Settlements Of A Building Due To Gypsum Dissolution, Minh Phong Luong

International Conference on Case Histories in Geotechnical Engineering

Geotechnical facts are presented relating to the damaging settlements of a building due to gypsum dissolution in the subsoil. Settlement records on the damaged building over a period of 15 months after first disturbances are given in correlation with the ground water pumping volumes from a well located in the neighbourhood in order to attempt a comprehensive interpretation of this case history.


Deformation Of Slopes Of Two Excavations In Soft Clays, C. W. Sheng May 1984

Deformation Of Slopes Of Two Excavations In Soft Clays, C. W. Sheng

International Conference on Case Histories in Geotechnical Engineering

Observed results concerning the movements of excavated slopes during and after excavation for two drydocks with different construction sequence have been described. FEM analysis has been conducted and discussed. The effect of heavy rains on the stability of slope improved by wellpoints has been presented.


Design Considerations And Long-Term Performance Of A Building Foundation In Clay, G. E. Bauer May 1984

Design Considerations And Long-Term Performance Of A Building Foundation In Clay, G. E. Bauer

International Conference on Case Histories in Geotechnical Engineering

Based on the results of a full-scale footing tests, spread footings were used instead of end-bearing piles to support a four storey building extension. Five proto-type footings were instrumented and the settlement behaviour was monitored over 13 years. Special construction procedures had to be employed to achieve compatible differential settlements between the individual footings and the adjacent existing building.


Discussions And Replies, E. J. Armstrong, G. W. Plant, D. H. Shields, John P. Sully, H. Taylor, R. K. Katti, Shri K. K. Moza, Shri D. R. Katti May 1984

Discussions And Replies, E. J. Armstrong, G. W. Plant, D. H. Shields, John P. Sully, H. Taylor, R. K. Katti, Shri K. K. Moza, Shri D. R. Katti

International Conference on Case Histories in Geotechnical Engineering

No abstract provided.


Down Drag On An Instrumental Bored Pile In Soft Clay, R. K. Bhandari, M. R. Soneja, Devendra Sharma May 1984

Down Drag On An Instrumental Bored Pile In Soft Clay, R. K. Bhandari, M. R. Soneja, Devendra Sharma

International Conference on Case Histories in Geotechnical Engineering

The paper reports result of a comprehensive full scale field study expressly undertaken to monitor negative drag on a large diameter, bored cast-in-place reinforced concrete pile installed to rock in a deep deposit of soft marine clay of pleistaceae to recent origin. The pile was instrumented with load cells and the ground around the pile with piezometers and settlement gauges. The negative drag was generated by loading the ground around the pile in stages. The ground settlements were accelerated by providing vertical sand drains. The observational data were utilized in figuring out the influence of surcharge on the depth of …


Dynamic Precompression Treatment - A Case History, F. J. Leon May 1984

Dynamic Precompression Treatment - A Case History, F. J. Leon

International Conference on Case Histories in Geotechnical Engineering

An unusual case history of a condominium apartment building, originally designed for eleven storeys, to which four additional floors were added after the footings had already been constructed and was successfully completed to fifteen storeys in height . The use of rather high soil-bearing values, from 7 ksf ( 350 kPa) in the original design to over 12 ksf ( 600 kPa) . The project site , underlain by erratic soil profiles containing layers of soft fine-grained soils to about 20 ft (6 m) below the surface, had been effectively improved with an intense application of the Dynamic Precompression Treatment …


Effect Of Foundation Deformations On The Damage Of A Masonry Villa (Case History), S. A. Abo-El Magd, H. M. Hosny, M. Mashhour May 1984

Effect Of Foundation Deformations On The Damage Of A Masonry Villa (Case History), S. A. Abo-El Magd, H. M. Hosny, M. Mashhour

International Conference on Case Histories in Geotechnical Engineering

Cracks in the masonry walls of a one storey villa due to foundation deformations are investigated in this paper. In spite of the fact that the soil formation in the site was found to be almost uniform, hogging deformation profile took place in the strip foundation due to unequal loading. Analysis of the walls together with their supporting soil, as one integrated system, showed that very small foundation deformation can produce tensile stresses in the wall higher than its tensile strength. Repair of the cracks was proposed and carried out successfully.


Embankment On Vertical Drains - Pore Pressures During Construction, M. Jamiolkowski, R. Lancellotta May 1984

Embankment On Vertical Drains - Pore Pressures During Construction, M. Jamiolkowski, R. Lancellotta

International Conference on Case Histories in Geotechnical Engineering

Excess pore pressures and consolidation settlements observed during the construction of a trial embankment placed on four different types of vertical drains are examined with the aim of evaluating: undrained pore pressure response, field coefficient of consolidation and drain performance.


Evaluation Of A Differentially Settled Tank, S. M. Gazioglu, J. L. Withiam May 1984

Evaluation Of A Differentially Settled Tank, S. M. Gazioglu, J. L. Withiam

International Conference on Case Histories in Geotechnical Engineering

The paper discusses studies undertaken to identify the cause(s) for differential settlements experienced by a large floating roof tank. The studies included an evaluation of existing subsurface and tank performance data, additional subsurface exploration and laboratory test programs, a monitoring program during the restricted use of the tank and recommended remedial measures to allow full use of the tank. It is concluded that the affected portion of the tank was sited over a thicker and more compressible soil layer than the remaining portions and that releveling by mudjacking would allow unrestricted future use of the tank.


Excessive Settlement In Buildings, A. Verghese Chummar May 1984

Excessive Settlement In Buildings, A. Verghese Chummar

International Conference on Case Histories in Geotechnical Engineering

The paper deals with three case studies where the foundations of buildings in the coastal areas of South India settled from 10 to 100 Cms resulting in excessive tilt or cracks in the superstructure. Details of soil exploration work carried out, description of the soil characteristics and the analysis of the causes of settlement are dealt with in this paper. The remedial measures suggested for the possible rectification of the damages are also presented.


Failure Of The Ghana Law School Building In Accra, Ghana, N. K. Kumapley, S. Ramachandra May 1984

Failure Of The Ghana Law School Building In Accra, Ghana, N. K. Kumapley, S. Ramachandra

International Conference on Case Histories in Geotechnical Engineering

The immediate post-independence era in Ghana, namely the late 1950's to early 1960's, was characterised by extensive physical and infrastructural development, for most of which proper design and construction records were either not kept or were lost. This has often led to difficulties when remedial measures have to be designed for some of these structures which have failed after only a few years in service. The paper describes attempts to diagnose the cause(s) of failure and to design remedial measures for one such structure in the absence of original construction records.


Field Consolidation Of A Moderately Organic Hetrogeneous Deposit, P. D. Deo, A. S. Mehta May 1984

Field Consolidation Of A Moderately Organic Hetrogeneous Deposit, P. D. Deo, A. S. Mehta

International Conference on Case Histories in Geotechnical Engineering

Very little technical information is available in literature about the compressibility characteristics of peat and organic soils. The problem of estimating consolidation settlements is even more complex for moderately organic hetrogeneous soils, such as mixtures of organic and inorganic soils.

Two known factors affecting compressibility characteristics of organic soils are: natural moisture content and consolidation pressure. From several sites, natural moisture content and compressibility data was collected for organic soils. The data is presented graphically for low and moderate consolidation pressures.

On the basis of the above mentioned data, coefficient of compression index for a moderately organic deposit was estimated. …


Field Observation Of Pore Pressure In Soft Clay, R. L. Wei May 1984

Field Observation Of Pore Pressure In Soft Clay, R. L. Wei

International Conference on Case Histories in Geotechnical Engineering

Pore pressure measurements made during the preloading of a large oil tank on a deep deposit of soft clay are reported and analyzed. The piezometer data show that the excess pore pressure at a point in the subsoil increases linearly with the increasing surface load until a certain critical load is reached. Then the induced shear stress at that point reaches the shearing strength of the soil, and local yield occurs. Henceforth there is a pronounced increase in the observed rate of pore pressure built-up.


Foundation Design And Construction For A Large Mill Complex, C. R. I. Clayton, J. Milititsky, L. J. L. Carvalho May 1984

Foundation Design And Construction For A Large Mill Complex, C. R. I. Clayton, J. Milititsky, L. J. L. Carvalho

International Conference on Case Histories in Geotechnical Engineering

Very little good field data exists concerning the performance of heavily loaded end-bearing piles on thin layers of weak rock. The problems associated with the foundations for silos are often severe, since loads are normally heavy, and allowable differential settlements are often very small. The paper describes just such problems, associated with the construction of a flour mill complex, where the principal problems were associated with the uncertainties of pile performance. On the basis of the uniaxial unconfined compressive strength of the supporting rock the end-bearing piles supporting silos within the mill appeared to be overloaded. A programme of slow …


Foundation Heave At Asco Ii Nuclear Power Plant, R. B. Fallgren, C. R. Mcclure May 1984

Foundation Heave At Asco Ii Nuclear Power Plant, R. B. Fallgren, C. R. Mcclure

International Conference on Case Histories in Geotechnical Engineering

Excavation of 75m of claystone at Asco Unit II resulted in foundation heave in excess of anticipated elastic rebound. The heave was found to be caused by expansive clay minerals in the rock swelling in the presence of water. Upper-bound estimates of future heave were made based on past trends, and structures analyzed to demonstrate their capacity to resist heave-caused deformations. The primary factor in controlling heave is the amount of water available to the bedrock.


Foundation Performance Of Very Old Structures, S. C. Handa May 1984

Foundation Performance Of Very Old Structures, S. C. Handa

International Conference on Case Histories in Geotechnical Engineering

Withstanding the agents of destruction for several centuries, some of the structures in this world, exist as a testimony to the sound and perfected techniques of construction used in years that belong to the bygone past. Among the most famous are Taj Mahal and Qutb Minar, still standing in a magnificent and sound condition. One of the wonders of the world, Taj Mahal though built in seventeenth century still looks so fresh that the super-structure performance also speaks of the adequate and perfect foundation that must have been built for it. This paper deals with subsoil conditions at site, the …


Foundation Problems And Solutions At The Bridge River, Powerhouse No. 1, H. Taylor, A. P. Joseph May 1984

Foundation Problems And Solutions At The Bridge River, Powerhouse No. 1, H. Taylor, A. P. Joseph

International Conference on Case Histories in Geotechnical Engineering

The Bridge River Powerhouse No. 1 was constructed between 1946 and 1950 on the north shore of Seton Lake near Lillooet, British Columbia, Canada. The Powerhouse contains four Pelton wheel (impulse) turbines generating a total of 200 MW of electrical power. When the powerhouse was completed and the first units placed in operation severe and extensive ground cracking occurred behind and beyond the powerhouse. The ground movement shifted the powerhouse slightly toward the lake, and cracked the concrete penstock tunnels. As a result of this the foundation under the powerhouse was thoroughly investigated and instrumentation installed to record and assess …


General Report For Theme One - Foundations For Structures And Failure Records, Robert C. Kirby, Guilaine Roussel May 1984

General Report For Theme One - Foundations For Structures And Failure Records, Robert C. Kirby, Guilaine Roussel

International Conference on Case Histories in Geotechnical Engineering

No abstract provided.


Geologic Considerations In Civil Constructions - Malaysian Case Studies, Boon K. Tan May 1984

Geologic Considerations In Civil Constructions - Malaysian Case Studies, Boon K. Tan

International Conference on Case Histories in Geotechnical Engineering

The need for adequate geologic input into civil engineering projects is common knowledge to all. However, quite surprisingly, in many construction projects in Malaysia geologic input is either totally lacking or highly inadequate. An indicator of the extent of neglect of geologic input into civil constructions in Malaysia is the fact that many soil investigation reports for these projects in this country do not contain a section or even a brief write-up on the site geology. This paper presents several case studies of civil engineering projects where geologic factors have been overlooked, thus resulting in the delay in the completion …


Geotechnical Problems And Performance Studies - Chilla Power Scheme, Hardwar, D. N. Bhargava, Dwarka Nath, S. N. Kapoor, Sunde Singh May 1984

Geotechnical Problems And Performance Studies - Chilla Power Scheme, Hardwar, D. N. Bhargava, Dwarka Nath, S. N. Kapoor, Sunde Singh

International Conference on Case Histories in Geotechnical Engineering

Thin plastic clay seams existing in the upper Shivalik formations caused hazardous geotechnical problems during the construction of 144 MW capacity Chilla Power House Scheme, Hardwar, India by initiating several land slides. In addition, serious seepage problems occurred with the commissioning of the scheme. The paper describes in detail, the events of slides & seepage problems faced and the remedial measures adopted to counteract them. The data observed on the instruments installed to keep a vigil on the performance of the structure has also been analysed and discussed.


Ground Heave Due To Pile Driving, J. P. Dugan Jr., D. L. Freed May 1984

Ground Heave Due To Pile Driving, J. P. Dugan Jr., D. L. Freed

International Conference on Case Histories in Geotechnical Engineering

The factors which influence ground heave due to pile driving outside the construction site are discussed. Elevation survey data are presented for nine case studies in the Boston area where the subsoil conditions consist of an insensitive clay deposit in the range of 60 to 110 feet thick. Curves of heave vs. normalized distance exhibit a trend of increasing heave with increased volumetric displacement ratio. Patterns of ground heave typically occur as radially shaped contours decreasing in magnitude away from pile driving. Building and ground movements observed several years after completion of pile driving indicate that the heave is temporary, …