Open Access. Powered by Scholars. Published by Universities.®

Education Commons

Open Access. Powered by Scholars. Published by Universities.®

Series

Arts and Humanities

Maine

Dickey-Lincoln School Lakes Project

Publication Year

Articles 1 - 3 of 3

Full-Text Articles in Education

Social Impact Summary : Dickey-Lincoln School Lakes Project / Prepared For The Department Of The Army, Corps Of Engineers, New England Division, Edward C. Jordan Company, Inc. Jan 1977

Social Impact Summary : Dickey-Lincoln School Lakes Project / Prepared For The Department Of The Army, Corps Of Engineers, New England Division, Edward C. Jordan Company, Inc.

Dickey-Lincoln School Lakes Project

The Dickey-Lincoln Hydroelectric Dam is a water resources project proposed by the Federal Government (U. S. Army Corps of Engineers). Therefore, in accordance with the National Environmental Policy Act, the Corps of Engineers is required to prepare an environmental impact statement (EIS) on the project. A federal plan or project such as Dickey-Lincoln should take into account its effect upon man's health, safety, welfare and economic well-being, as well as effects upon the surrounding environment. More importantly, project plans should be evaluated in a "manner calculated to encourage harmony between man and his environment." In other words, project plans or …


Summary Of Labor Impacts During Construction : Dickey-Lincoln School Lakes Project, Edward C. Jordan Company, Inc. Jan 1977

Summary Of Labor Impacts During Construction : Dickey-Lincoln School Lakes Project, Edward C. Jordan Company, Inc.

Dickey-Lincoln School Lakes Project

This study is to assess the effects or impacts of construction and operation of the Dickey-Lincoln hydroelectric project upon the people in the St. John Valley, Maine, and New England. Having determined the effects of the project, a second objective is to discuss mitigation of defined adverse impacts. More specifically, this study attempts to identify adverse impacts and deal with how to minimize such impacts if at all possible.


Social And Economic Consequences Of The Dickey-Lincoln School Hydro-Electric Power Development On The Upper St. John Valley, Maine -- : Phase 1, Preconstruction, Louis A. Ploch, Nelson L. Leray Jan 1968

Social And Economic Consequences Of The Dickey-Lincoln School Hydro-Electric Power Development On The Upper St. John Valley, Maine -- : Phase 1, Preconstruction, Louis A. Ploch, Nelson L. Leray

Dickey-Lincoln School Lakes Project

The intention of this report is to present a still picture of the selected area as of the summer of 1966. The emphasis is on empirical relationships. The data contained herein will provide a base for subsequent analysis. Thus little attempt is made to cast the findings of the study in a theoretical framework. Later publications will utilize relevant theory and research to analyze the social and economic changes in an area related to the building of the Dickey and Lincoln School Dams. It is presumed that this particular report and its statistical sup-plement will be of particular interest to …