Dickey-Lincoln School Lakes Project At Dickey, Maine : Draft Supplement Environmental Impact Statement, U.S. Army Engineer Division, New England Division
Dickey-Lincoln School Lakes Project At Dickey, Maine : Draft Supplement Environmental Impact Statement, U.S. Army Engineer Division, New England Division
Dickey-Lincoln School Lakes Project
The purpose of this Draft Supplement (SDEIS) to the Revised Draft Environmental Impact Statement (RDEIS) is to evaluate the environmental impacts of the Fish and Wildlife Mitigation Plan proposed for Implementation in conjunction with development of the Dickey-Lincoln School Lakes Project, Maine (Appendix K, RDEIS and Attachment 1 of the Report). Although the mitigation plan is intended to mitigate rather than impose adverse environmental impacts, the mitigation measures proposed do constitute a major Federal action requiring the development of a supplemental environmental impact statement pursuant to the National Environmental Policy Act of 1969.
Final Report On The Recreation Plan For Dickey-Lincoln School Lakes Project, Maine : Prepared For The Corps Of Engineers, New England Division, Northern Maine Regional Planning Commission, Land Use Consultants, Inc
Final Report On The Recreation Plan For Dickey-Lincoln School Lakes Project, Maine : Prepared For The Corps Of Engineers, New England Division, Northern Maine Regional Planning Commission, Land Use Consultants, Inc
Dickey-Lincoln School Lakes Project
The purpose of this report is to evaluate and describe the existing recreational use and resources of the project area and the encompassing study area and to project the future use of those resources both with and without the Dickey-Lincoln School Lakes Project. This study develops and evaluates a concept plan for the recreation potential of the Dickey-Lincoln School project and assesses the recreational impact of this recommended concept plan.
Transmission Planning Summary : Dickey-Lincoln School Lakes Project Transmission Studies, United States Department Of Interior
Transmission Planning Summary : Dickey-Lincoln School Lakes Project Transmission Studies, United States Department Of Interior
Dickey-Lincoln School Lakes Project
This report summarizes the results of system planning, environmental, and location studies for transmission facilities associated with the proposed Dickey-Lincoln School Lakes Project in northern Maine. The studies recommend the construction of two 345-kV transmission circuits from a substation near the project along a route through western Maine into northern New Hampshire and Vermont. The plan will integrate the power produced by the project into the New England Power Pool Transmission System. Five alternate integration plans were identified and studied. Of the five plans, the recommended plan, which calls for the lines to be suspended from a single row of …
Hydroelectric Power Potential At Corps Of Engineers Projects : A Report, Ralph L. Trisko, United States. Army., Institiute For Water Resources
Hydroelectric Power Potential At Corps Of Engineers Projects : A Report, Ralph L. Trisko, United States. Army., Institiute For Water Resources
Dickey-Lincoln School Lakes Project
This report completes phase one of the study. It is intended to fill the need, recognized at the outset, for a broad framework within which subsequent more detailed study at the project level might take place. It is an overview of physical hydropower potential in the context of energy and water resources and demands, energy economics, and federal policy, organization, and practices pertaining to hydropower development and marketing.