Walking Box Ranch Planning And Design Quarterly Progress Report: Period Ending July 10, 2012, Margaret N. Rees Jul 2012

Walking Box Ranch Planning And Design Quarterly Progress Report: Period Ending July 10, 2012, Margaret N. Rees

Walking Box Ranch

  • BLM informed UNLV that after investigating a concession contract as the appropriate BLM document for the future operating partner, they have concluded that an operating agreement is the preferred document and they are proceeding to complete such an agreement as soon as possible.
  • Following a visit to the ranch with BLM, UNLV has completed temporary repairs to ranch house windows, which should mitigate deterioration of the ranch house from water
  • UNLV participated in a one-half day meeting with BLM to review Condit’s Extended Content Package #1. As a result of the lack of progress by Condit, UNLV was requested to …


Walking Box Ranch Planning And Design Quarterly Progress Report: Period Ending April 10, 2012, Margaret N. Rees Apr 2012

Walking Box Ranch Planning And Design Quarterly Progress Report: Period Ending April 10, 2012, Margaret N. Rees

Walking Box Ranch

  • BLM informed UNLV that the type of operating plan that was identified in June, 2011 as the appropriate instrument for future operations, and which was to have been completed by May 2012, prior to beginning construction, would not work for BLM. BLM informed UNLV that they are now considering a concession contract as the appropriate BLM document for the future operating partner.
  • BLM and UNLV visited the ranch for a day to examine the continuing deterioration of the ranch house from water, and to discuss how to address this on-going problem. The group reviewed damage owing to water coming into …


Walking Box Ranch Planning And Design Quarterly Progress Report: Period Ending January 10, 2012, Margaret N. Rees Jan 2012

Walking Box Ranch Planning And Design Quarterly Progress Report: Period Ending January 10, 2012, Margaret N. Rees

Walking Box Ranch

  • UNLV’s President Smatresk has reiterated his commitment to the WBR project and has further committed full funding for IT and security costs.
  • UNLV participated in a one-half day meeting with BLM to discuss the future WBR operating agreement between BLM and UNLV; UNLV participated in a 1.5 day meeting to review the 100% Design drawings.
  • UNLV continues to wait on BLM for direction on how to mitigate the continuing deterioration of the ranch house.
  • Weather station research continues and has produced the following this past quarter. 1) Ground-source heat pump (GSHP) Vs Photovoltaic (PV) technology: A detailed analysis comparing these …