Dickey-Lincoln School Lakes Project At Dickey, Maine : Final Environmental Statement, Volume 1-4, U. S. Army Engineer Division, New England
Dickey-Lincoln School Lakes Project At Dickey, Maine : Final Environmental Statement, Volume 1-4, U. S. Army Engineer Division, New England
Dickey-Lincoln School Lakes Project
The proposed Dickey-Lincoln School Lakes Project in northern Maine is a multipurpose installation on the St.John River. The combination hydroelectric power and flood control project is located in Aroostook County, Maine, near the Canadian border. The two proposed earth fill dams located at Dickey are 10,200 feet in length with a maximum height of 335 feet. They would impound 7.7 million acre feet of water at a maximum pool elevation 910 feet mean sea level. A second earth filled dam located 11 miles downstream at Lincoln School would serve as a regulatory dam. It would be 2100 feet in lenqth, …
Federal Water Pollution Control Act Section "404" Evaluation For Dickey-Lincoln School Lakes, New England Division, United States Army Engineer Division, United States Army Corps Of Engineers
Federal Water Pollution Control Act Section "404" Evaluation For Dickey-Lincoln School Lakes, New England Division, United States Army Engineer Division, United States Army Corps Of Engineers
Dickey-Lincoln School Lakes Project
The purpose of this report is to relate various aspects of the proposed Dickey-Lincoln School Lakes Hydroelectric Project to appropriate considerations defined by Section 404 of the Federal Water Pollution Control Act of 1972.
Revised Draft Impact Statement Issued For Dickey-Lincoln, New England Division, United States Army Corps Of Engineers
Revised Draft Impact Statement Issued For Dickey-Lincoln, New England Division, United States Army Corps Of Engineers
Dickey-Lincoln School Lakes Project
The revised draft combines data previously published in two separate impact statements prepared by the Corps relating to the dams, reservoirs and Power Plants and by the U. S. Department of Energy for transmission facilities to link the St. John River development to the New England power grid.
Transmission Reconnaissance Study : Dickey-Lincoln School Lakes Project, United States Department Of Interior
Transmission Reconnaissance Study : Dickey-Lincoln School Lakes Project, United States Department Of Interior
Dickey-Lincoln School Lakes Project
Two dams are proposed on the St. John River in northern Maine: Dickey, a high earth filled dam immediately above the confluence of the Allagash with the St. John, will have an installed generating capacity of 760 MW; and Lincoln School Dam, 11 miles downstream, a capacity of 70 MW. These dams are scheduled for completion during the mid 1980's. The U.S. Corps of Engineers, New England Division, has been allocated funds to design the project and prepare their own environmental impact statement. This report (Transmission Reconnaissance Studies) discusses alternative transmission facilities needed to connect the project with the New …
Fact Sheet : Dickey-Lincoln School Lakes, Maine, New England Division, United States Army Corps Of Engineers
Fact Sheet : Dickey-Lincoln School Lakes, Maine, New England Division, United States Army Corps Of Engineers
Dickey-Lincoln School Lakes Project
The purpose of the proposed Dickey-Lincoln School Lakes Hydroelectric Project is to convert the natural energy of the upper St. John River in northern Maine for use as a source of electricity to meet future needs of New England consumers.
A Study Of The Dickey-Lincoln Hydroelectric Project And Its Impact On The Resources Of The Upper Saint John River Valley, Rosemary M. Manning, Sierra Club, New England Chapter
A Study Of The Dickey-Lincoln Hydroelectric Project And Its Impact On The Resources Of The Upper Saint John River Valley, Rosemary M. Manning, Sierra Club, New England Chapter
Dickey-Lincoln School Lakes Project
This report was under-taken primarily to evaluate the impact that the construction of the Dickey-Lincoln project would have upon the resources of the Upper St. John River, and to examine the assertion that the Dickey-Lincoln project constitutes a wise use of the public's environmental and economic resources. Since the case that has been made for the construction of the Dickey-Lincoln project rest primarily on the justification of the project in economic terms, this aspect of the project proposal will be intensively explored.