Open Access. Powered by Scholars. Published by Universities.®

Architecture Commons

Open Access. Powered by Scholars. Published by Universities.®

The University of Maine

Water resources development

Life Sciences

Publication Year

Articles 1 - 7 of 7

Full-Text Articles in Architecture

Dickey-Lincoln School Lakes Project Environmental Impact Statement: Appendix J: Coordination With Other Agencies & Public Involvement (Supplement), New England Division, United States Army Corps Of Engineers Jan 1978

Dickey-Lincoln School Lakes Project Environmental Impact Statement: Appendix J: Coordination With Other Agencies & Public Involvement (Supplement), New England Division, United States Army Corps Of Engineers

Dickey-Lincoln School Lakes Project

This agency will be particularly concerned about any impact which this project might have on any existing, proposed or known units of the National Park System, or any known historic, natural or environmental education sites which are currently part of , or eligible for, the National Landmark Program. This report is a planning aid for the proposed Dickey-Lincoln Dams and Reservoirs project in Maine. A number of endangered, rare, or unique animal species are known or suspected to occur in the project area.


Draft Environmental Impact Statement : Dickey-Lincoln School Lakes Transmission Project, United States Department Of Energy Jan 1978

Draft Environmental Impact Statement : Dickey-Lincoln School Lakes Transmission Project, United States Department Of Energy

Dickey-Lincoln School Lakes Project

This draft environmental impact statement (EIS) will describe the environmental impacts of transmission plans of the Department of Energy (DOE) for the proposed Dickey-Lincoln School Lakes Project. Electric power produced by the project is to be integrated into the New England electric system if the project is constructed.


Transmission Reconnaissance Study : Dickey-Lincoln School Lakes Project, United States Department Of Interior Jan 1977

Transmission Reconnaissance Study : Dickey-Lincoln School Lakes Project, United States Department Of Interior

Dickey-Lincoln School Lakes Project

Two dams are proposed on the St. John River in northern Maine: Dickey, a high earth filled dam immediately above the confluence of the Allagash with the St. John, will have an installed generating capacity of 760 MW; and Lincoln School Dam, 11 miles downstream, a capacity of 70 MW. These dams are scheduled for completion during the mid 1980's. The U.S. Corps of Engineers, New England Division, has been allocated funds to design the project and prepare their own environmental impact statement. This report (Transmission Reconnaissance Studies) discusses alternative transmission facilities needed to connect the project with the New …


Recommendations Of Alternative System Plans And Transmission Corridors For The Dickey/Lincoln School Hydroelectric Project, Vtn Environmental Sciences (Firm), Interior Jan 1976

Recommendations Of Alternative System Plans And Transmission Corridors For The Dickey/Lincoln School Hydroelectric Project, Vtn Environmental Sciences (Firm), Interior

Dickey-Lincoln School Lakes Project

This second volume of the Assessment of Alternative Power Transmission Corri-dors related to the Dickey Lincoln/School Hydroelectric Project, contains all relevant background materials to support the mapping and analysis of en-vironmental resource information. Narrative explaining what information was evaluated and the sources and reasons for its consideration are integral to this assessment.


Transmission Planning Summary : Dickey-Lincoln School Lakes Project Transmission Studies, United States Department Of Interior Jan 1976

Transmission Planning Summary : Dickey-Lincoln School Lakes Project Transmission Studies, United States Department Of Interior

Dickey-Lincoln School Lakes Project

This report summarizes the results of system planning, environmental, and location studies for transmission facilities associated with the proposed Dickey-Lincoln School Lakes Project in northern Maine. The studies recommend the construction of two 345-kV transmission circuits from a substation near the project along a route through western Maine into northern New Hampshire and Vermont. The plan will integrate the power produced by the project into the New England Power Pool Transmission System. Five alternate integration plans were identified and studied. Of the five plans, the recommended plan, which calls for the lines to be suspended from a single row of …


Water Resources Development Project, Saint John River Basin : Dickey-Lincoln School Lakes, Maine, U.S.A. And Quebec, Canada : Design Memorandum No. 2 : Hydrology And Hydraulic Analysis, Section Iv - Lincoln School Dam-Spillway Design Flood, Department Of The Army, New England Division, Corps Of Engineers Jan 1976

Water Resources Development Project, Saint John River Basin : Dickey-Lincoln School Lakes, Maine, U.S.A. And Quebec, Canada : Design Memorandum No. 2 : Hydrology And Hydraulic Analysis, Section Iv - Lincoln School Dam-Spillway Design Flood, Department Of The Army, New England Division, Corps Of Engineers

Dickey-Lincoln School Lakes Project

The first of four sections comprising Design Memo-randum No. 2. The other sections are: II - Dickey Dam - Spillway Design Flood, III - Lincoln School Dam - Spillway Design Flood and IV - Flood Analysis and Reservoir Regulation. la section I, hydro-logic studies will be confined generally to the drainage area of the Saint John River above the gaging station at Fort Kent, Maine. The purpose of section I is to present the climatological and streamflow data for the Saint John River above Fort Kent in order to establish hydrologic criteria for the design of the Dickey and Lincoln …


Scope Of Work, Environmental Impact Statement For The Dickey-Lincoln School Lakes Project, New England Division, United States Army Engineer Division, United States Army Corps Of Engineers Jan 1975

Scope Of Work, Environmental Impact Statement For The Dickey-Lincoln School Lakes Project, New England Division, United States Army Engineer Division, United States Army Corps Of Engineers

Dickey-Lincoln School Lakes Project

Revised draft combines data previously published in two separate impact statements prepared by the corps relating to the dams, reservoirs and power plants and by the U. S. Department of Energy for transmission facilities to link the St. John River development to the New England power grid. The latter agency is responsible for the marketing and distribution of power generated at federally-financed installations.