Open Access. Powered by Scholars. Published by Universities.®

Physical Sciences and Mathematics Commons

Open Access. Powered by Scholars. Published by Universities.®

Ecology and Evolutionary Biology

2009

Wildlife Monitoring

Articles 1 - 4 of 4

Full-Text Articles in Physical Sciences and Mathematics

Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending December 31, 2009, Margaret N. Rees Dec 2009

Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending December 31, 2009, Margaret N. Rees

Wildlife Monitoring

Project 1. Relict Leopard Frog Monitoring, Management, and Research

  • All milestones and deliverables are on schedule
  • Fall surveys at all sites have been completed
  • Mark-recapture surveys scheduled for fall were completed
  • Short-term habitat improvements at two sites were conducted
  • RLFCT meeting was hosted
  • Draft annual report was written and presented at the RLFCT meeting

Project 2. Bald Eagle Winter Monitoring and Evaluation

  • All milestones and deliverables are on schedule
  • An annual project review presentation was given to Clark County
  • A draft final report was written and submitted to Clark County
  • All data for this project was transferred to the County …


Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending September 30, 2009, Margaret N. Rees Sep 2009

Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending September 30, 2009, Margaret N. Rees

Wildlife Monitoring

Project 1. Relict Leopard Frog Monitoring, Management, and Research

  • All milestones and deliverables associated with this MSHCP project are on schedule
  • Mark-recapture surveys scheduled for fall have been initiated
  • Two potential sites for translocations were visited to assess water availability
  • Coordination continues on an upcoming translocation

Project 2. Bald Eagle Winter Monitoring and Evaluation

  • All MSHCP milestones and deliverables are on schedule
  • An annual project review presentation was given to Clark County

Project 3. Peregrine Falcon Monitoring and Evaluation

  • This MSHCP project is on schedule for all milestones and deliverables
  • Monitoring of Peregrine falcon 2009 breeding activities has been completed …


Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending June 30, 2009, Margaret N. Rees Jun 2009

Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending June 30, 2009, Margaret N. Rees

Wildlife Monitoring

Project 1. Relict Leopard Frog Monitoring, Management, and Research

  • All milestones and deliverables associated with the MSHCP project are on schedule
  • Translocation field season has been completed
  • Spring monitoring surveys have been completed
  • Dana Drake, UNLV Research Assistant, has left the project

Project 2. Bald Eagle Winter Monitoring and Evaluation

  • All MSHCP milestones and deliverables are on schedule

Project 3. Peregrine Falcon Monitoring and Evaluation

  • The MSHCP projects are on schedule for all milestones and deliverables
  • Peregrine falcon monitoring of breeding activities are ongoing and are nearing completion
  • Method testing of active survey methodology has been completed
  • Stacy Crowe was …


Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending March 31, 2009, Margaret N. Rees Mar 2009

Lake Mead National Recreation Area Monitoring And Evaluation Of Sensitive Wildlife: Quarterly Progress Report, Period Ending March 31, 2009, Margaret N. Rees

Wildlife Monitoring

Project 1. Relict Leopard Frog Monitoring, Management, and Research

  • Translocation field season has begun; eggs have been collected, tadpoles are being reared and some tadpoles have been released to an existing translocation site
  • Egg mass surveys for the season have been completed
  • Nocturnal surveys have begun
  • Sampling for the amphibian chytrid fungus conducted at multiple sites
  • Data transferal to County conducted this quarter
  • A modified annual work plan and timeline was provided for delivery to the County
  • All milestones and deliverables associated with the MSHCP project are on schedule

Project 2. Bald Eagle Winter Monitoring and Evaluation

  • Winter bald eagle …