The Multi– Mode Resource– Constrained Project Scheduling Problem With Generalized Precedence Relations, Bert De Reyck, Willy Herroelen
The Multi– Mode Resource– Constrained Project Scheduling Problem With Generalized Precedence Relations, Bert De Reyck, Willy Herroelen
Research Collection Lee Kong Chian School Of Business
In this paper, we tackle the challenging problem of scheduling activities to minimize the project duration, in which the activities (a) are subject to generalized precedence relations, (b) require units of multiple renewable, non-renewable and doubly constrained resources for which a limited availability is imposed, and (c) can be performed in one of several different ways, reflected in multiple activity scenarios or modes. These multiple modes give rise to several kinds of tradeoffs (time/resource, time/cost and resource/resource trade-offs) which allow for a more effcient allocation and use of resources. We present a local search-based solution methodology which is able to …
A Classification Scheme For Project Scheduling Problems, Willy Herroelen, Erik Demeulemeester, Bert De Reyck
A Classification Scheme For Project Scheduling Problems, Willy Herroelen, Erik Demeulemeester, Bert De Reyck
Research Collection Lee Kong Chian School Of Business
The basic concern of scheduling is commonly described as the allocation of limited resources to tasks over time (Lawler et al. 1993, Pinedo 1995). The resources and tasks may take many forms. In project scheduling the tasks refer to the activities belonging to one or more projects. The execution of project activities may require the use of different types of resources (money, crews, equipment, …). The scheduling objectives may also take many forms (minimizing project duration, minimizing project costs, maximizing project revenues, optimizing due date performance,…). The result is a wide and steadily growing variety of problem types which motivates …
Algorithms For Scheduling Projects With Generalized Precedence Relations, Bert De Reyck, Erik Demeulemeester, Willy Herroelen
Algorithms For Scheduling Projects With Generalized Precedence Relations, Bert De Reyck, Erik Demeulemeester, Willy Herroelen
Research Collection Lee Kong Chian School Of Business
The problem of scheduling projects under various types of resource constraints constitutes an important and challenging problem which has received increasing attention during the past several years. The bulk of the models and procedures designed for coping with these problem types aim at scheduling project activities to minimize the project duration subject to constant availability constraints on the required set of resources and precedence constraints that indicate that activities can only be started when all of their predecessors have already been finished. However, real-life project scheduling applications often involve more complicated types of precedence relations such as arbitrary minimal and …