Dickey-Lincoln School Lakes, Maine, U.S.A. And Quebec, Canada: Design Memorandum No. 3: Hydropower Capacity And Project Economic, New England Division, United States Army Corps Of Engineers Jan 1976

Dickey-Lincoln School Lakes, Maine, U.S.A. And Quebec, Canada: Design Memorandum No. 3: Hydropower Capacity And Project Economic, New England Division, United States Army Corps Of Engineers

Dickey-Lincoln School Lakes Project

This design memorandum presents the results of current engineering and economic analyses which serve as the basis for the selection of the recommended hydro-power installation at the Dickey-Lincoln School Lakes project. The report includes a summary of data pertinent to hydropower features of the project, projections of electricity needs for the New England Power Supply Areas, a description of the recom-mended power plan and facilities, pertinent data associated with power regulation studies, and the economic and engineering rationale for capacity optimization.


Transmission Planning Summary : Dickey-Lincoln School Lakes Project Transmission Studies, United States Department Of Interior Jan 1976

Transmission Planning Summary : Dickey-Lincoln School Lakes Project Transmission Studies, United States Department Of Interior

Dickey-Lincoln School Lakes Project

This report summarizes the results of system planning, environmental, and location studies for transmission facilities associated with the proposed Dickey-Lincoln School Lakes Project in northern Maine. The studies recommend the construction of two 345-kV transmission circuits from a substation near the project along a route through western Maine into northern New Hampshire and Vermont. The plan will integrate the power produced by the project into the New England Power Pool Transmission System. Five alternate integration plans were identified and studied. Of the five plans, the recommended plan, which calls for the lines to be suspended from a single row of …


Water Resources Development Project, Saint John River Basin : Dickey-Lincoln School Lakes, Maine, U.S.A. And Quebec, Canada : Design Memorandum No. 2 : Hydrology And Hydraulic Analysis, Section Iv - Lincoln School Dam-Spillway Design Flood, Department Of The Army, New England Division, Corps Of Engineers Jan 1976

Water Resources Development Project, Saint John River Basin : Dickey-Lincoln School Lakes, Maine, U.S.A. And Quebec, Canada : Design Memorandum No. 2 : Hydrology And Hydraulic Analysis, Section Iv - Lincoln School Dam-Spillway Design Flood, Department Of The Army, New England Division, Corps Of Engineers

Dickey-Lincoln School Lakes Project

The first of four sections comprising Design Memo-randum No. 2. The other sections are: II - Dickey Dam - Spillway Design Flood, III - Lincoln School Dam - Spillway Design Flood and IV - Flood Analysis and Reservoir Regulation. la section I, hydro-logic studies will be confined generally to the drainage area of the Saint John River above the gaging station at Fort Kent, Maine. The purpose of section I is to present the climatological and streamflow data for the Saint John River above Fort Kent in order to establish hydrologic criteria for the design of the Dickey and Lincoln …