Clements V. T. R. Bechtel Co., Jesse W. Carter
Clements V. T. R. Bechtel Co., Jesse W. Carter
Jesse Carter Opinions
Contractors stated a cause of action for foreclosure of a mechanic's lien, having complied with the statutory requirements, and matters essential to the cause of action should not have been stricken by the trial court.
M. F. Kemper Constr. Co. V. Los Angeles [Dissent], Jesse W. Carter
M. F. Kemper Constr. Co. V. Los Angeles [Dissent], Jesse W. Carter
Jesse Carter Opinions
Construction company that submitted erroneous bid was entitled to rescission on the ground of unilateral mistake because city knew of the error before it accepted the bid and the city was restored to status quo by accepting the next lowest bid.