In 2008, excavation work continued on areas surrounding the domus of the North-East Church complex and expanded into areas west of Cardo 2 North. In addition, probes to bedrock were conducted in several areas of the site. Conservation efforts were completed on F538 in the north aisle and F580 in the skeuophylakion. This report will address work done in the following areas:
- Cardo 2 North (“Via Sacra”) and Related Buildings
- Structures to the South of the South Hall and the Diakonikon
- The Areas West of the Portico
- Probe in the Nave
- The Eastern Street and Related Buildings
- Conservation Efforts